| |
|
Decks are a perfect area for
outdoor entertaining and outdoor relaxing. The style of
deck you choose to build determines how you use your deck,
as well as how you build it. Although similar in
appearance, different decks can require different
construction techniques.
Out Installation Services Associates built this Multievel
deck and documented the steps taken in order to help you
build your own outdoor living area. |
|
|
|
Siding was
removed and ledger boards attached to the house. The
ledger boards establish the upper-deck level that will be
28 feet long by 15 feet wide. This upper level fits into
an inner corner of the house. Batterboards and mason's
string lines were used to locate footing positions for
both levels of the deck.
Approximate time for a novice (with a helper) to lay out
footing locations for this deck: 15-17 hours, which
includes removing siding and attaching the ledger. |
 |
| |
|
Thirteen
12-inch-diameter footing holes were dug. Each hole is 48
inches deep to get below the local frost line. The bottoms
of the holes didn't need flaring, but tube forms were
required. Concrete was delivered by truck and pumped
through a hose to each footing location. Post anchors for
6x6 posts were attached to the footings after the concrete
cured for 48 hours. Large footings and posts allowed for
the fewest number possible for a multilevel deck of this
size. |
 |
| |
|
6x6 POSTS were
installed and temporarily braced in position. A water
level was used to establish post heights for each level.
Posts were then trimmed at the correct height. Beams made
from doubled 2x12s will sit on the posts. Joists will be
cantilevered over beams on both deck levels. The lower
deck level is 28 feet by 16 feet. |
 |
| |
|
Beams were
built in place and attached to the post tops with
adjustable post caps. The long beams were made longer than
required and will be trimmed flush with the rim joists
after the joists are installed. The short beam supports
the upper-deck level joists that attach at the patio door
bay. The bay framing isn't strong enough to anchor a
standard ledger board. Beams were covered with
self-sealing membrane for extra moisture protection. |
 |
| |
|
A ledger for
the lower-deck level was attached to the posts beneath the
middle beam. The ledger sits in notches cut in the posts.
Then a 2x12 header joist and rim joists were installed for
both deck levels. Forty-five degree corners were made on
the lower level where stairs to ground level will be
built. Beam ends were trimmed flush with the rim joists.
The inner 2x12 joists were attached with blocking in the
middle of the joist spans on both levels. |
 |
| |
|
5/4x6 decking
was installed perpendicular to the joists on the upper
level. Decking was installed at opposite diagonals on the
lower level. Deck screws were used to fasten the decking.
The different decking patterns provide visual texture and
separate the two levels. A double joist was installed at
the center of the lower level to properly support the
decking. |
 |
| |
|
Locations were
established for 8-inch-diameter footings at the bottom
ends of the stairs. One side of each stair run rests on a
preexisting concrete slab. Only one additional footing was
necessary for each stair run. Stair runs were calculated
and stringers made, and the stairs were built. Each stair
run ends on a low-level deck platform. A simple box stair
connects the two deck levels. The levels could be farther
apart and connected by longer stair runs.
Approximate time (not including the low-level platforms) |
 |
| |
|
Railing post
locations were calculated and the posts installed. Posts
were notched and attached to the outside of the perimeter
framing and the stringers. Coated metal tubes are used as
balusters for this railing. |
 |
| |
|
|
|
|
|
RELATED PROJECTS
Building a Ground-Level Deck
Building a Single-Level Raised Deck
Building a Low-Level Deck
|
|
|
|
|